Documentation › Glossary
Glossary
The terms the product uses, in the sense it uses them.
Schedule
| Term | Meaning |
|---|---|
| Data date | The date progress is recorded to. Work before it is actual; work after it is scheduled. |
| Early and late dates | The earliest and latest an activity can start and finish without delaying the project. |
| Total float | How long an activity can slip without moving the project finish. Negative float means a constraint or must-finish date is already missed. |
| Critical | An activity with total float at or below the critical threshold (zero by default). |
| Retained logic / progress override | How an in-progress activity's remaining work treats incomplete predecessors: waits for them, or ignores them. |
| Level of effort | An activity whose duration follows the activities it is linked to, for support work. |
| Leveling | Delaying work so that no resource exceeds its limit. |
| Baseline | The schedule kept at a point in time, to measure against. The active baseline is the performance measurement baseline. |
| Must finish by | The project's required finish; the variance against it is reported beside the baseline variance. |
Earned value
| Term | Meaning |
|---|---|
| BAC | Budget at completion: the baseline's total. |
| PV, EV, AC | Planned value (what should have been done by the data date), earned value (what was done, at budget), actual cost (what it cost). |
| SV, CV | Schedule variance EV − PV; cost variance EV − AC. |
| SPI, CPI | Schedule performance index EV ÷ PV; cost performance index EV ÷ AC. Below 1 is behind or over. |
| EAC, ETC, VAC | Estimate at completion (remaining work at budget, or at the performance to date), estimate to complete, variance at completion BAC − EAC. |
| TCPI | The cost performance needed on the remaining work to finish within the BAC or the EAC. |
| Period index | SPI and CPI for the work since the last recorded update, as opposed to cumulative to date. |
| Steps (rules of credit) | Weighted steps on an activity that give its percent complete. |
Risk
| Term | Meaning |
|---|---|
| Three-point estimate | Minimum, most likely and maximum duration, as a triangle, BetaPERT or uniform distribution. |
| Monte Carlo, Latin hypercube | Sampling every estimate thousands of times and rescheduling each time; Latin hypercube spreads the samples evenly for a steadier result. |
| P50, P80, P90 | The date (or cost) with a 50, 80 or 90 percent chance of being met. |
| Deterministic | The single-point schedule without uncertainty, and the probability the run gives it. |
| Criticality, sensitivity | How often an activity was critical across the iterations; how strongly its duration correlates with the finish. |
| Risk factor | One driver (productivity, design maturity) that scales the durations of the activities it is assigned to. |
| Register | The list of threats and opportunities, assessed before and after the response, with actions. |
| Joint confidence | The chance of meeting both the finish and the cost together. |
Estimating
| Term | Meaning |
|---|---|
| Estimate class | How well defined the scope was when the estimate was made: Class 5 (concept screening, 0–2% defined) to Class 1 (check estimate, 65–100% defined), after the AACE International practice. |
| Accuracy range | The expected range around the total for the class, narrow and wide. |
| Basis of estimate | The document stating scope, inclusions, exclusions, assumptions, methodology, sources and allowances. |
| Assembly, norm | A unit of work with its labour hours, material and equipment per unit. |
| Rate set | The build-up from a base wage to an all-in rate. |
| Contingency | The amount added for the risks within the scope, as a percentage or from the risk analysis at a confidence level. |
| Escalation | Price change from the cost basis date to when the money is spent. |
Organization
| Term | Meaning |
|---|---|
| OBS | Organizational breakdown structure: who is responsible, as a tree. |
| WBS | Work breakdown structure: what the work is, as a tree. |
| Portfolio | A set of projects reviewed together. |
| Workspace | A cloud space with members, projects and an enterprise setup. |