Estimator guide
The Estimator builds a classed estimate from quantities and norms, prices it with your own rates and quotes, documents the basis, and hands it to the Planner as a resource-loaded baseline. This guide follows the tabs from left to right.

The header: class, basis date, currency
Every estimate carries a class, from Class 5 at concept screening to Class 1 at detailed design, in the manner of the AACE International classification practice. The class bar states the definition range, the end use and the methodology expected, and the accuracy range around the total, narrow and wide. The cost basis date is the date the prices are good for; escalation runs from it. Hours a day and days a week set crew durations and equipment day rates.
Takeoff
Enter quantities by commodity from drawings or a model: feet of pipe, welds, supports, cable, concrete. Takeoff quantities feed the estimate lines that reference them, so a revised takeoff reprices the lines.
Estimate
The WBS on the left shows each node's total. A node's lines are on the right. A line is a quantity of work with, per unit, the labour hours by craft or crew, material, equipment hours, subcontract, expenses and other costs; or a lump sum from a quote or an allowance. Three methods:
- Assembly: quantity times a norm from the library (hours per unit by crew, material per unit, equipment per unit), with a productivity factor for site conditions.
- Quote: a vendor or subcontractor price, with its reference and date.
- Allowance: a judged amount for scope not yet defined, flagged as such in the basis.
The BOM import turns a bill of material into lines; Import sheet reads an existing estimate from a spreadsheet with column mapping.
Libraries
The libraries hold what the lines price from: crafts (a trade at a level with its base wage), rate sets (the build-up from wage to all-in rate: statutory payroll costs, benefits, small tools, overhead, profit), crews (a mix of crafts priced at the blended rate), equipment (day, week or month rates), materials (unit cost, waste, supplier, quote reference, price date, lead time, weight, currency) and assemblies (the norms). A catalogue generator builds assemblies from a reference CSV. Everything in the sample is illustrative; replace it with your own.
Totals
The build-up from direct cost by type (labour, material, equipment, subcontract, expenses, other) through markups, escalation by phase or on the cash flow, base cost, contingency and risk allowance to the total, with the currency exposure of foreign-priced items. Contingency is a percentage or comes from the risk analysis at your confidence level.
Risk log
Threats and opportunities with probability and three-point cost and schedule impacts before and after the response, the response and its cost, actions and owners. The log scores on your matrix, computes the expected value, and with the Risk analysis contingency method runs a Monte Carlo over the lines' uncertainty and the risk events to give the contingency at P50, P80 or the level you choose. The log travels to the Planner with the estimate.
Schedule
A baseline schedule from the estimate: the WBS becomes the work breakdown, lines become activities with durations from crew hours and crew sizes, in the phase order with your logic. Open in the Planner hands it over with the resources and rate sets, the quantities, the risk log and the estimate's class and reference, so the schedule starts as a resource-loaded baseline aligned to the estimate.
Cash flow
The estimate spread over the schedule by period, by cost type and by WBS, with escalation applied month by month when that method is chosen. Exports to CSV and to the Excel workbook.
Benchmarks
A database of past projects' actuals, kept apart from any estimate: unit rates and ratios by work type and location, normalised by a location factor. Compare the estimate's rates and ratios against them to spot lines that are out of line, and record this estimate's outcome later to grow the database.
Revisions
Each revision is kept with its total and a note. Compare any two: which lines changed, by how much, and why.
Summary, Basis and Report
Summary is the one-page view by WBS and cost type with the class, the accuracy range and the contingency. Basis is the basis of estimate: scope, inclusions, exclusions, assumptions, deliverables, contracting, execution and risks as you write them, plus the generated parts (methodology, libraries used, quotes and their dates, allowances). Report prints the estimate pack through the browser.
Files and Excel
The estimate is kept in the browser between visits and saved as a .estimate.json file with Save (Ctrl + S). Excel writes a workbook: summary, estimate detail, by WBS, labour rates, materials, cash flow and the risk register. The benchmark database exports and imports separately.
The assistant
The ✦ Assistant button opens a panel that answers questions about the open estimate: what drives the total, what is missing for the class, whether the contingency matches the risks logged, and it drafts basis of estimate text. See The assistant.