Learn › Earned value management

Earned value management

Earned value management (EVM) answers two questions with one set of numbers: are we getting the work done that we planned, and is it costing what we planned? It compares the value of work planned, the value of work done and the cost of that work, period by period, and turns them into variances, the CPI and SPI indexes and a forecast at completion.

The three measures

MeasureAlso calledMeaning
Planned value (PV)BCWSThe budget of the work scheduled to be done by a date, from the baseline.
Earned value (EV)BCWPThe budget of the work actually done by that date: each activity's budget times its percent complete.
Actual cost (AC)ACWPWhat the work done actually cost, from timesheets, invoices and accruals.
Budget at completion (BAC)The total budget: PV at the end of the baseline.

The key idea is that EV is measured in budget dollars (or hours), not in time or spend. That puts schedule and cost performance on the same scale.

Variances, indexes and forecasts

NameFormulaRead it as
Cost varianceCV = EV − ACNegative: the work done cost more than its budget.
Schedule varianceSV = EV − PVNegative: less work done than planned by now.
Cost performance indexCPI = EV / ACValue earned per dollar spent; below 1 is over cost.
Schedule performance indexSPI = EV / PVWork done per unit of work planned; below 1 is behind.
Estimate at completionEAC = BAC / CPIThe final cost if the cost efficiency so far continues.
Estimate to completeETC = EAC − ACWhat is still to be spent.
Variance at completionVAC = BAC − EACThe expected overrun (negative) or underrun at the end.
To-complete performance indexTCPI = (BAC − EV) / (BAC − AC)The cost efficiency the remaining work needs to finish on budget.

BAC / CPI is the simplest forecast and the one most often cited; other EACs (for example, ones that also weigh the SPI, or a bottom-up re-estimate of the remaining work) are used where the past is a poor guide to the future. Whatever the method, say which one a report uses.

A worked example

A project has a budget of $1,000,000. At the end of month four the baseline says $400,000 of work should be done (PV). The work actually done is worth $360,000 of budget (EV), and it cost $400,000 (AC).

Making it work in practice

Earned value in DeltaSys

DeltaSys calculates PV, EV and AC from the schedule, its baseline, progress (including weighted steps and installed quantities) and actuals from timesheets, contractor invoices and accruals. It records each update, so CPI and SPI can be compared week on week or month on month as well as to date, with S-curves, thresholds and the forecast at completion, by project, WBS, cost account or across the portfolio.

Questions

Is earned value only for large government projects?

No. Any project with a budget, a schedule and a way to measure progress can use it; the calculation is the same at any size.

Can earned value be in hours instead of dollars?

Yes. Labour hours are often a better measure of field productivity than dollars, because they are not distorted by material prices or rates.

Next: reading CPI and SPI · schedule risk analysis.

See it on real schedules. The DeltaSys demo opens in the browser with seven illustrative projects: schedules, earned value, estimates, risk and the portfolio, every window open to browse. Open the demo · Pricing · Documentation

Primavera and P6 are trademarks of Oracle Corporation; Microsoft Project is a trademark of Microsoft Corporation; PMBOK is a trademark of the Project Management Institute; AACE is a trademark of AACE International; Last Planner is a registered trademark of the Lean Construction Institute. DeltaSys is not affiliated with or endorsed by them. Standards are described in our own words; see the publications themselves for their text.