Learn › AACE estimate classes

AACE estimate classes 1 to 5 explained

AACE International classifies cost estimates into five classes, from Class 5 (a screening estimate with almost no project definition) to Class 1 (a check estimate on a fully defined project). The class is set by one thing above all: how far the project's definition has progressed. Matching an estimate's class to the decision it supports is one of the simplest ways to avoid funding a project on numbers that could not bear the weight.

The principle: maturity of definition

AACE's classification matrix uses the maturity of the project definition deliverables, expressed as a percentage of complete definition, as the primary characteristic. The other characteristics (what the estimate is used for, how it is prepared, its expected accuracy and the effort to prepare it) follow from that maturity. An estimate is not Class 3 because someone calls it Class 3; it is Class 3 because the scope, engineering and plan behind it are developed to that level.

The five classes

ClassProject definitionTypical useTypical method
Class 5About 0% to 2%Screening or feasibilityFactors, parametric models or judgment
Class 4About 1% to 15%Concept study or feasibilityMostly factored and parametric
Class 3About 10% to 40%Budget authorization or controlMixed: factored for some parts, detailed for others
Class 2About 30% to 75%Control, or a bid or tenderMostly detailed unit costs and quantities
Class 1About 65% to 100%Check estimate, or a bid or tenderDetailed: quantities, unit costs, crews and productivity

The ranges overlap deliberately: definition does not jump between classes, and the boundaries are judgment calls supported by evidence.

Accuracy

Expected accuracy widens as definition falls. AACE expresses it as a range relative to Class 1: in the generic matrix, a Class 5 estimate's range is typically 4 to 20 times as wide as a Class 1 estimate's, Class 3 about 2 to 6 times, Class 2 about 1 to 3 times. Ranges are asymmetric, wider on the high side than the low, because projects overrun far more often and further than they underrun. Industry-specific recommended practices give the ranges as percentages for their sector. Accuracy is a range around the estimate, not a promise, and contingency is how it is funded.

Showing which class an estimate is

A credible class is backed by deliverables, not adjectives: the status of the scope statement, process or system definition, layouts, equipment lists, design drawings, the execution plan, the schedule and the contracting strategy. A good basis of estimate lists them, with their status, and states the class the evidence supports. When the evidence supports a lower class than the one claimed, either the estimate is relabelled or the gaps are closed before the decision.

Estimate and schedule classes together

AACE also classifies schedules by maturity. The same logic applies: a Class 3 estimate funded on a Class 5 schedule has a cost with no credible time basis behind it. Keeping the two at the same class, and handing the estimate to the schedule as its resource-loaded baseline, keeps cost and time telling the same story.

Estimate classes in DeltaSys

The DeltaSys Estimator records each estimate's class, checks it against a deliverables checklist and shows which class the evidence actually supports, runs reviews to a sign-off, writes the basis of estimate, and sets contingency by risk analysis. Its range rules start from company defaults by class, which your organization replaces with its own. The estimate passes to the Planner as a resource-loaded baseline with its class, so every project shows whether its estimate and schedule classes agree.

Sources

AACE International, Recommended Practice 17R-97, Cost Estimate Classification System; and Skills and Knowledge of Cost Engineering, 6th edition, chapter 9 (Cost Estimating), Figure 9.1. Industry-specific practices, such as 18R-97 for process industries, apply the system to particular sectors. Read the recommended practices for their full text and tables.

Questions

Which class should a funding decision use?

Most capital projects make the final funding decision on a Class 3 estimate: enough definition for the accuracy a commitment of funds needs. Owners typically prepare Class 5 and Class 4 themselves, and engineering contractors often prepare Class 3 and better.

Can a Class 5 estimate be accurate?

It can turn out close, but its expected range is wide because so little is defined. The classification describes what the estimate can be relied on for, not how lucky it was.

Related: cost risk and contingency · earned value management.

See it on real schedules. The DeltaSys demo opens in the browser with seven illustrative projects: schedules, earned value, estimates, risk and the portfolio, every window open to browse. Open the demo · Pricing · Documentation

Primavera and P6 are trademarks of Oracle Corporation; Microsoft Project is a trademark of Microsoft Corporation; PMBOK is a trademark of the Project Management Institute; AACE is a trademark of AACE International; Last Planner is a registered trademark of the Lean Construction Institute. DeltaSys is not affiliated with or endorsed by them. Standards are described in our own words; see the publications themselves for their text.